Why the Next Well Should Start With a Better Review of the Last One 

A completed well should not be treated as the end of the story. It should become the starting point for the next drilling decision, the next cost estimate, and the next plan. When teams move too quickly from one well to another without a proper review, they risk carrying the same assumptions, delays, and cost issues into the next program. 

For operators and drilling teams, the end of a well is one of the best times to learn. The data is fresh, the field experience is still clear, and the team can see which parts of the plan worked in practice. A strong drilling performance review helps turn that information into practical improvements before the next well is planned. 

Why post-well review matters 

A post-well review is not just a closeout exercise. It is a way to understand what happened, why it happened, and what should change before the next well. The goal is not to create another report that sits in a folder. The goal is to turn drilling experience into better planning, cost control, and execution. 

The Journal of Petroleum Technology has highlighted that well planning can use lessons learned and best practices to optimize well construction, and that post-well analysis has historically been one way performance gains are identified (Schlumberger, 2017). This reinforces an important point: if the team does not review performance properly, valuable learning can stay trapped in individual memory instead of becoming part of the next plan. 

A good review helps the team look beyond whether the well was completed. It asks whether the plan was realistic, whether the cost estimate reflected field reality, whether the contractors were aligned, whether decision-making was timely, and whether the next well can be improved. 

The last well can improve the next well plan 

Every well produces lessons. Some are technical. Some are operational. Some are commercial. The value comes from capturing them clearly enough that they can be used before the next drilling program begins. 

A useful drilling performance review should look at: 

  • Planned versus actual drilling days 
  • Planned versus actual cost 
  • Non-productive time and invisible lost time 
  • Contractor and service performance 
  • Equipment readiness and reliability 
  • Hole problems, losses, influxes, or pressure issues 
  • Casing, cementing, mud, bit, and directional performance 
  • Logistics and site readiness 
  • Daily reporting quality 
  • Key decisions made during the well 
  • Lessons that should change the next drilling program 

These points help the team move from basic closeout to practical improvement. The more clearly the team understands the last well, the better it can plan the next one. 

Lessons learned should not be treated as a formality 

Many drilling teams already include a “lessons learned” section in end-of-well reports. The issue is not whether lessons are recorded. The issue is whether they are specific, practical, and used. 

A vague lesson such as “improve communication” does not help the next well. A useful lesson explains what communication failed, when it failed, who needed the information, what decision was affected, and how the process should change next time. 

A Journal of Petroleum Technology article on drilling and completion optimization noted that the drilling engineer’s role included planning the well, communicating the plan, monitoring parameters, ensuring compliance with the plan, cataloging lessons learned, and applying those lessons to new optimization plans (Baez et al., 2013). That sequence matters because lessons learned only create value when they are carried back into planning and execution. 

For operators, the question should be direct: did the last well teach us something that will change the next one? If the answer is no, the review may not be going deep enough. 

Cost movement deserves a closer look 

A drilling cost variance is not just a finance issue. It is usually a sign that something changed in planning, execution, scope, service performance, or field conditions. A post-well review should identify where cost moved and why. 

The team should review whether cost increases came from expected uncertainty, avoidable delay, contractor performance, equipment issues, logistics, pressure-related events, or changes to the drilling program. This helps separate normal drilling variability from repeatable problems that should be addressed before the next well. 

This is especially important when preparing the next AFE. If the last estimate missed key cost drivers, the next estimate should not repeat the same assumptions. A better review helps the next AFE become more realistic, more useful, and more connected to field performance. 

Non-productive time should be reviewed by cause, not just amount 

Non-productive time is often tracked as a total number, but the total alone does not tell the full story. To improve future performance, teams need to understand what caused the time loss and whether it was avoidable. 

For example, NPT caused by weather is different from NPT caused by late equipment, unclear responsibilities, poor contractor coordination, or a well plan that did not reflect actual conditions. Each cause requires a different response. 

A drilling performance review should classify time loss clearly enough to guide action. If the team cannot explain where time was lost, the next well may repeat the same problem without anyone seeing the pattern. 

Invisible lost time can be just as important 

Not every performance issue appears as obvious downtime. Some losses happen inside normal operations. These may include slow tripping, inefficient connections, repeated minor delays, avoidable waiting time, or activities that take longer than planned but do not get classified as major NPT. 

The Journal of Petroleum Technology has discussed the use of drilling-specific KPIs to compare operational efficiency and improve drilling phases, including examples related to tripping speeds, connection times, rate of penetration, mechanical specific energy, and BOP test times (Schlumberger, 2017). 

This is why a strong drilling performance review should not only ask, “Where did we stop?” It should also ask, “Where did we move slower than we should have?” Small inefficiencies can become meaningful when repeated across multiple wells. 

Contractor performance should be part of the review 

Drilling performance depends on more than the operator’s internal team. Rig crews, directional drilling providers, mud companies, cementing crews, logistics providers, construction teams, pressure control specialists, and other service providers all affect the final outcome. 

A post-well review should look at whether contractors were ready, aligned, and able to deliver their scope as planned. The goal is not to assign blame. The goal is to understand what worked, what needs improvement, and what should be clarified before the next job. 

This can help the team strengthen scopes of work, adjust service timing, improve handoffs, and make expectations clearer before the next well. Better contractor alignment before the next program can reduce confusion once operations begin. 

The end-of-well report should support future decisions 

An end-of-well report should be more than a record of what happened. It should be structured in a way that helps future teams make better decisions. 

A useful end-of-well report should include enough detail to help the next planning team understand: 

  • What was planned 
  • What actually happened 
  • Where time was gained or lost 
  • Where cost moved 
  • Which assumptions were correct 
  • Which assumptions were wrong 
  • What risks appeared during operations 
  • How the team responded 
  • Which lessons should change the next well 
  • What should be repeated because it worked 

When an end-of-well report is written this way, it becomes a planning asset. It helps teams avoid starting from scratch and gives the next well a stronger foundation. 

Data matters, but context matters more 

Modern drilling programs generate daily reports, cost data, operational metrics, service reports, and technical records. These are useful, but data alone does not explain performance. 

A well may show extra days in a section, but the team still needs to understand why. Was it formation behavior, equipment readiness, hole cleaning, directional difficulty, pressure control, weather, logistics, or decision delay? The answer matters because the next well should not be planned from the number alone. 

This is where experienced review adds value. People who understand drilling operations can connect the data with field context, technical judgment, and practical next steps. 

A good review should work with the existing team 

A drilling performance review should not feel like an outside party judging the people who delivered the well. The most useful reviews are collaborative. They work with the existing team and help turn their experience into better planning. 

The operator’s team understands the asset, the internal process, the commercial goal, and the decisions made during the well. Support from an experienced drilling partner should strengthen that understanding, not replace it. 

The goal is to help the team see patterns, ask better questions, document useful lessons, and carry those lessons into the next drilling program. That approach respects the work already done while helping the next well benefit from it. 

What to review before planning the next well 

Before the next drilling program starts, the team should use the last well as a practical reference. The review should not wait until the next AFE is already built or the next plan is nearly finished. It should happen early enough to influence the next set of decisions. 

Project teams should ask: 

  • What did the last well teach us? 
  • Which assumptions were accurate? 
  • Which assumptions were too optimistic? 
  • Where did the most time move? 
  • Where did the most cost move? 
  • Which delays were avoidable? 
  • Which contractors performed well? 
  • Which scopes need to be clearer next time? 
  • Did the field team have the information it needed? 
  • What should change in the next drilling program? 

These questions help the next well start from evidence, not habit. They also help teams avoid repeating problems simply because no one captured the lesson clearly enough. 

The commercial value of better post-well review 

A better post-well review can support better cost estimates, stronger drilling programs, improved contractor coordination, and more realistic planning. Over time, this can improve how teams approach multi-well campaigns, repeat wells, and technically demanding projects. 

The commercial value is not only in finding mistakes. It is in finding what should be repeated, what should be changed, and what should be planned differently before the next well starts spending money. 

For operators, this makes post-well review a cost-control tool, a planning tool, and a performance improvement tool. It helps the team turn completed work into better future decisions. 

Practical support before the next program 

Teams that are reviewing completed wells or preparing the next drilling program may benefit from experienced support that can connect field results with planning decisions. BOAX supports drilling teams across drilling management, professional engineering, project management, drilling operations, construction services, and managed pressure drilling. 

That support can help operators review well performance, understand cost and time movement, improve the next drilling program, and turn lessons learned into practical planning changes. The purpose is not to take over the existing team. It is to work with the team, strengthen the review process, and help the next well start with better information. 

Final thought 

The next well should not begin with a blank page. It should begin with a clear understanding of what the last well taught the team. 

A strong drilling performance review helps operators turn completed work into better planning, better cost control, and better execution. It gives the next well the benefit of real experience instead of repeated assumptions. 

When the review is specific, honest, and practical, it becomes more than a closeout task. It becomes one of the most useful steps in planning the next well. 

References 

Baez, F., & Flores, O. (2013, September 30). Management strategies optimize drilling and completion operations. Journal of Petroleum Technology. https://jpt.spe.org/management-strategies-optimize-drilling-and-completion-operations 

Schlumberger. (2017, January 11). Well construction performance service bridges planning-execution gap to boost efficiency. Journal of Petroleum Technology. https://jpt.spe.org/well-construction-performance-service-bridges-planning-execution-gap-boost-efficiency 

Society of Petroleum Engineers. (2026). Case studies in challenging drilling environments: Innovations, lessons learned, and performance improvements. SPE Annual Technical Conference and Exhibition. https://www.atce.org/2026-technical-program-1/case-studies-in-challenging-drilling-environmentsnbsp-innovations-lessons-learned-and-performance-improvements 

Leave a comment